Construction Update – 11/23/21

Questions?

Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535

Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771

Public Water Main Construction Update

  • All water main and public water services have been installed and put into service. Please coordinate with Mid City to schedule completion of the private property work.
  • Contact Isak Fruchtman to report any issues related to property damage as the result of the construction: 414.982.2300 x1535, Isak.Fruchtman@strand.com
  • Pavement milling is scheduled to take place by the end of November. Paving may take place in November, weather permitting. Any paving not completed this fall will be rescheduled to springtime.
  • Turf areas and landscaping disturbed by construction will be restored this year. Vinton will return in Spring to reseed any areas that have not germinated.

See the chart below for the anticipated schedule for other work areas.

Work AreaProject LocationAnticipated Start Date
(Subject to Change)
AGood Hope Road from W. Main Street to Lannon Road (Good Hope Road Closed to Thru Traffic; Follow Posted Detour)Complete
BLannon Road from W. Main Street to the north (Lannon Road Closed to Thru Traffic; Follow Posted Detour)In Progress
CW. Main Street from Townline Road to Flagstone Pass (W. Main Street Closed to Southbound Traffic; Follow Posted Detour)Complete
DGood Hope Road from Lannon Road to east of Emerald Drive (Good Hope Road Open to Thru Traffic; Traffic Pattern Shift)In Progress
EDiamond Drive from Good Hope Road to the south (Diamond Drive Closed to Thru Traffic)In Progress
FW. Edgewood Drive and Circle Drive (W. Edgewood Drive and Circle Drive Closed to Thru Traffic)In Progress
GW. Main Street and Townline Road Roundabout (W. Main Street Closed to Southbound Traffic and Townline Road Closed to Northbound Traffic; Follow Posted Detour)Complete
HState Street, Hemlock Lane, Bay Street, N. Lake Street, and Vine Street (Roads Closed to Thru Traffic)In Progress
ILannon Road from Elementary School to Diamond Drive (Lannon Road Open to Thru Traffic; Temporary One Lane Closure)In Progress
JParkview Drive and Forestview Drive (Parkview Drive and Forestview Drive Closed to Thru Traffic)In Progress
KGood Hope Private Driveway (West of Lannon Elementary) (Good Hope Private Driveway Closed to Thru Traffic)Complete
LTownline Road from W. Main Street to the north (Townline Road Closed to Thru Traffic; Follow Posted Detour)Complete
MF and W Court (F and W Court Closed to Thru Traffic)In Progress
Water Service Expansion Work Zones

Construction Update – 11/19/21

Questions?

Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535

Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771

Public Water Main Construction Update

  • Vinton currently anticipates completing all water main construction by the end of November.
  • Contact Isak Fruchtman to report any issues related to property damage as the result of the construction: 414.982.2300 x1535, Isak.Fruchtman@strand.com
  • Work is actively occurring on Good Hope Road, Diamond Drive, Hemlock Lane, Bay Street, State Street, Vine Street, Lake Street, Lannon Road, F and W Court, W Forest View Drive, N Parkview Drive, Edgewood Drive, and Circle Drive.
  • All streets with trench patches will receive full width paving.
  • Pavement milling is scheduled to take place by the end of November. Paving may take place in November, weather permitting. Any paving not completed this fall will be rescheduled to springtime.
  • Turf areas and landscaping disturbed by construction will be restored this year. Vinton will return in Spring to reseed any areas that have not germinated.

See the chart below for the anticipated schedule for other work areas.

Construction Update – 11/12/21

Questions?

Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535

Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771

Public Water Main Construction Update

  • Vinton currently anticipates completing all water main construction by the end of November.
  • Contact Isak Fruchtman to report any issues related to property damage as the result of the construction: 414.982.2300 x1535, Isak.Fruchtman@strand.com
  • Work is actively occurring on Good Hope Road, Diamond Drive, Hemlock Lane, Bay Street, State Street, Vine Street, Lake Street, Lannon Road, F and W Court, W Forest View Drive, N Parkview Drive, Edgewood Drive, and Circle Drive.
  • Pavement milling is scheduled to take place by the end of November. Paving may take place, weather permitting. Any paving not completed this fall will be rescheduled to springtime.
  • Turf areas and landscaping disturbed by construction will be restored this year. Vinton will return in Spring to reseed any areas that have not germinated.
  • The Well Upgrades project was awarded on 10/11. Construction will likely begin in November.

See the chart below for the anticipated schedule for other work areas.

Construction Update – 11/05/21

Questions?

Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535

Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771

Public Water Main and Well Construction Update

  • Vinton currently anticipates completing all water main construction by the end of November, weather permitting.
  • Vinton is using 5-6 construction crews in order to accomplish this.
  • Mid-City has re-mobilized to Lannon to complete private property conversions to municipal water prior to 12/31/21.
  • Work is actively occurring on Good Hope Road, Diamond Drive, Hemlock Lane, Bay Street, State Street, Vine Street, Lake Street, Lannon Road, F and W Court, W Forest View Drive, N Parkview Drive, Edgewood Drive, and Circle Drive.
  • Pavement and landscape restoration will be occurring within the next couple of weeks.
  • Turf areas disturbed by construction will be restored this year. Vinton will return in Spring to repair any areas that have not germinated.
  • Expect temporary interruptions to driveway access. A project representative will knock on your door prior to driveway interruptions. If your driveway is blocked and you need access, step outside and ask a project representative. In most cases, access can be temporarily restored within 15 minutes.
  • The Well Upgrades project was awarded on 10/11. Construction will likely begin in November.

See the chart below for the anticipated schedule for other work areas.

Construction Update – 10/28/21

Questions?

Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535

Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771

Public Water Main and Well Construction Update

  • Vinton currently anticipates completing all water main construction by the end of November, weather permitting.
  • Vinton is using 5-6 construction crews in order to accomplish this.
  • Mid-City has re-mobilized to Lannon to complete private property conversions to municipal water prior to 12/31/21.
  • Work is actively occurring on Good Hope Road, Diamond Drive, Hemlock Lane, Bay Street, State Street, Vine Street, Lake Street, Lannon Road, Edgewood Drive, and Circle Drive.
  • Pavement restoration will be occurring within the next couple of weeks.
  • Curb and gutter installation on Good Hope Road will occur next week. Residents effected by the interruption will receive notifications.
  • Expect temporary interruptions to driveway access. A project representative will knock on your door prior to driveway interruptions. If your driveway is blocked and you need access, step outside and ask a project representative. In most cases, access can be temporarily restored within 15 minutes.
  • The Well Upgrades project was awarded on 10/11. Construction will likely begin in November.

See the chart below for the anticipated schedule for other work areas.

Construction Update – 10/15/21

Questions?

Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535

Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771

Public Water Main and Well Construction Update

  • Vinton currently anticipates completing all water main construction by the first week of December, weather permitting.
  • Water main is currently being installed on Good Hope Road, Diamond Drive, Hemlock Lane, Bay Street, Edgewood Drive, and Circle Drive.
  • Expect temporary interruptions to driveway access. A project representative will knock on your door prior to driveway interruptions. If your driveway is blocked and you need access, step outside and ask a project representative. In most cases, access can be temporarily restored within 15 minutes.
  • Town Line Road will be closed through approximately 10/22 as pavement and landscape restoration is completed.
  • Good Hope Road will have a traffic pattern shift through 11/22. During work hours, this may include a single lane with a flagger
  • The Well Upgrades project was awarded on 10/11. Construction will likely begin in November.

See the chart below for the anticipated schedule for other work areas.

Construction Update – 10/05/21

Questions?

Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535

Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771

Public Water Main and Well Construction Update

  • Town Line Road will be closed through approximately 10/22.
  • Good Hope Road will have a traffic pattern shift from 10/4 through 11/22.
  • Edgewood & Circle Dr. will begin on 10/11 and continue through 11/19.
  • Diamond Drive, near Good Hope Rd., will begin approximately on 10/18.

The construction notification for this project can be found here.

See the chart below for the anticipated schedule for other work areas.

Construction Update – 9/09/21

Questions?

Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535

Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771

Public Water Main and Well Construction Update

  • Main Street will be closed to Westbound traffic through approximately September 20, 2021.
  • Town Line Road will be closed to Northbound traffic through approximately September 20, 2021 and then closed to all thru traffic through approximately October 22, 2021.
  • Restoration in Work Zone C, W. Main Street from Townline Road to Flagstone Pass will be completed by 9/11.
  • Work through the Lannon Elementary School Easement was completed.
  • Water main on Lannon Rd. (Work Zone I) from Lannon Elementary to Forestview was completed. However, the remaining water main to Diamond Drive and public water service laterals are not planned to be installed until October. Restoration of the trenched area will take place the week of 9/13.
  • Restoration in Work Zone G, through the roundabout, is in progress and will be completed .
  • See the chart below for the anticipated schedule for other work areas.

The construction notification for this project can be found here.

See the chart below for the anticipated schedule for other work areas.

Construction Update – 9/02/21

Questions?

Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535

Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771

Public Water Main and Well Construction Update

  • Main Street will be closed to Westbound Traffic through approximately October 1st or later.
  • Work Zone C, W. Main Street from Townline Road to Flagstone Pass:
    • Water main has been installed
    • Restoration will take place the week of 9/7.
  • Work through the Lannon Elementary School Easement began and will be completed by September 3.
  • Work on Lannon Rd. (Work Zone I) began. However, public water service laterals are not planned to be installed until October. Restoration of the trenched area will take place the week of 9/7.
  • Work Zone G, through the roundabout, will begin the week of 9/7.
  • See the chart below for the anticipated schedule for other work areas.

Construction Update – 8/27/21

Questions?

Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535

Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771

Public Water Main and Well Construction Update

  • Work Zone C, W. Main Street from Townline Road to Flagstone Pass:
    • Westbound lane closure and partial detour is in effect.
    • No westbound traffic is allowed.
    • Water main installation will continue through early September.
  • Work through the Lannon Elementary School Easement began and will be completed by September 3.
  • See the chart below for the anticipated schedule for other work areas.

Severe Weather Update – 8/12/21

  • The Village’s municipal water system has backup power supplied by a permanent, natural gas generator.
  • During the recent storms, the wellhouse’s main power supply was interrupted.
  • The power supply automatically switched over to the natural gas generator.
  • The well and booster pumps continue to run on the generator without issue.
  • Water utility customers have reported no disruption to water service during this event.

Construction Update – 8/19/21

Questions?

Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535

Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771

Public Water Main and Well Construction Update

  • Work Zone C, W. Main Street from Townline Road to Flagstone Pass:
    • Westbound lane closure and partial detour is in effect.
    • No westbound traffic is allowed.
    • Water main installation started the week of 8/2 and will continue for the rest of August.
  • See the chart below for the anticipated schedule for other work areas.

Public Water Main and Well Construction Update – 8/06/21

  • Work Zone A, Good Hope Road from Main Street to Lannon Road:
    • Work is complete with minor restoration to continue.
  • Work Zone K, Good Hope Private Driveway (West of Lannon Elementary):
    • Work is complete with minor restoration to continue.
  • Work Zone C, W. Main Street from Townline Road to Flagstone Pass:
    • Westbound lane closure and partial detour started 8/2.
    •  Water main installation started the week of 8/2.

Public Water Main and Well Construction Update – 7/8/21

  • Lake Street storm sewer lining is being conducted by Visu-Sewer as part of the overall project and will take place during the month of July
  • Work Zone A, Good Hope Road from Main Street to Lannon Road, will continue.
    • Water main and public lateral installation are anticipated be completed by 7/9, with disinfection and testing completed by 7/14.
    • Contractor will begin grading and installing curb and gutter the week of 7/12.
  • Work Zone K, Good Hope Private Driveway (West of Lannon Elementary), will begin the week of 7/12.
  • See the chart below for the anticipated schedule for other work areas. Note: On-going schedule modifications are taking place in order to accommodate Cars on Main and Lannon 90th festivities.

Public Water Main and Well Construction Update – 7/2/21

  • No work will take place from Saturday, 7/3 through Monday, 7-5.
  • Lake Street storm sewer lining is being conducted by Visu-Sewer as part of the overall project and will take place during the month of July
  • Work Zone A, Good Hope Road from Main Street to Lannon Road, will continue.
    • Water main and public lateral installation are anticipated be completed the week of 7/6, with disinfection and testing completed by 7/14.
    • Contractor will begin grading and installing curb and gutter by approximately 7/8.
  • Work Zone K, Good Hope Private Driveway (West of Lannon Elementary), will begin on 7/8.
  • See the chart below for the anticipated schedule for other work areas.

Public Water Main and Well Construction Update – 6/7/21

  • USDA-RD has delivered “closing instructions” to the Village, signifying their approval of the application documents.
  • The Village Board awarded the public water main construction bid to Vinton Construction Company of Two Rivers, WI.
  • Vinton’s low bid of $5,459,392.50 was less than the USDA-RD budget.
  • Water Main Construction should start by the end of June or early July.
  • The area that Vinton plans to start work will be updated on this page as soon as the information is available.
  • Water main installation is scheduled for completion by the end of 2021.
  • Roadway construction is scheduled for completion by June of 2022.
  • Well upgrades are expected to proceed in the Fall of 2021.

WELL ABANDONMENT GRANT UPDATE – 12/15/20

  1. Well estimate forms are at Village Hall and on the Village’s website.
  2. Well Abandonment Grant applications are due approximately 1 month prior to the start of well abandonment work on your property.
    • Applications are not due by December 10th as indicated in the letter sent to residents impacted by the project.
    • DNR indicated they need to be submitted before the work is done.
    • Mid-City and CTW do not plan to start well abandonments until March.
    • Please apply by the end of February 2021.
  3. If your taxable income will be less in 2020 than it was in 2019, it is to your advantage to wait until January to submit your well abandonment grant form. Well Abandonment Grant eligibility is based on the income of the most recent full year’s taxable income. Contact Sandy Chancellor at DNR for special circumstances such as  a recent change in employment: (608) 275-3206.