CONSTRUCTION UPDATE – 07/15/22
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN CONSTRUCTION UPDATE
Vinton’s contract completion date has been extended to August 28, 2022 to allow time for lawn restoration and seed germination to take place.
The Village’s onsite construction Representative, Isak Fruchtman of Strand Associates, conducted an additional walk through of the entire project area related to surface/lawn restoration on Friday 7/8/22. The attached PDF is a plan set that marks out the area on each property that needs the contractor’s (Vinton) attention. This was sent to the Contractor on 7/14/22. You can view this markup by clicking on the following link: Outstanding Restoration Items For Vinton as of 7/8/22. Conduct a word search for your house number (i.e., “7349”) to find your specific property more efficiently.
Specific concerns should be directed to Isak from Strand at 414.982.2300 x1535 or Isak.Fruchtman@strand.com.
CONSTRUCTION UPDATE – 05/25/22
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN CONSTRUCTION UPDATE
The Village conducted a “punch list” walk through with Vinton, the public water main contractor, on Friday May 20th and Monday May 23rd. The purpose of the walk through was to generate a list of items to be completed or corrected. This included a review of each property affected by the public water main construction. Vinton and their subcontractors will be working over the course of the next few weeks to address the noted items. This includes some fine-grading and re-seeding on most properties. If you feel that something has still not been addressed AFTER the restoration has been done, please contact Isak from Strand at 414.982.2300 x1535.
Also be aware that a similar walk through has yet to occur related to the work of Mid City, the Village’s private property plumbing contractor. Mid City has a contractual obligation to come back for landscape restoration on the properties they disturbed. Mid City’s restoration work will likely begin in June.
The Village Board took action on May 24, 2022 to allow Mid City to continue to work on properties beyond the June 1, 2022 deadline on the condition that by that date 1) the owner of the property has completed their consent agreement to allow Mid City to do the work, and 2) Mid City has pulled a building permit to do the work on that property. Property owners that have not signed a consent agreement and have not had a building permit pulled for the work necessary to connect their property to municipal water on or before June 1, 2022 should prepare for enforcement action by the Village.
CONSTRUCTION UPDATE – 01/21/22
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN CONSTRUCTION UPDATE
This notice has been sent to everyone in the Village as a general update. The Contractor has completed installation and testing of all water mains. In 2021, approximately 150 residential properties have connected. Work at the well sites will be starting in 2022. This includes upgrading the Lannon Estates well to municipal grade, rehabilitating the well at Whispering Ridge, and adding a third booster pump to Whispering Ridge. These projects make the entire system more reliable and add fire protection capacity. This winter, the Village will be exploring how to use USDA-RD contingency grant funds made possible due to the projects tracking under budget.
RESTORATION WORK
Now that snow has arrived, the Contractor is likely unable to complete all restoration work. However, they are required to come back in Spring 2022 to complete whatever cannot be finished. The Village has not signed off on or paid for final restoration work and will do a comprehensive review in the spring of the entire project area. Restoration work is also part of the 1-year project warranty period. For example, any seeded areas that do not grow will be re-seeded in the spring. In the meantime, if you have an important or unique restoration need, please contact the field engineer: Isak Fruchtman, Isak.Fruchtman@strand.com, 414-982-2300 x1535.
OPTION TO KEEP YOUR WELL FOR OUTDOOR USE
The Village Board approved an ordinance in November 2021 to allow residents who have connected to municipal water to keep their well for outdoor use. Well Operation Permit forms are available at Village Hall and online at www.villageoflannon.com/water. Property owners have 90 days after connecting to municipal water to apply for a permit or to abandon their well. The cost of well abandonment that happens within that time frame is 100% covered by the Quarry Grant Fund (there is no longer a 50% match requirement).
Continue to visit www.villageoflannon.com/water for periodic updates.
CONSTRUCTION UPDATE – 12/23/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN CONSTRUCTION UPDATE
- RESTORATION WORK: The Contractor is likely unable to complete all restoration work before snow arrives. However, they are required to come back in Spring 2022 to complete whatever cannot be finished. The Village has not signed off on or paid for final restoration work and will do a comprehensive review in the spring of the entire project area. Restoration work is also part of the 1-year project warranty period. For example, any seeded areas that do not grow will be re-seeded in the spring. In the meantime, if you have an important or unique restoration need, please contact the field engineer: Isak Fruchtman, Isak.Fruchtman@strand.com, 414-982-2300 x1535.
- The Contractor has completed installation and testing of all water mains.
- Approximately 150 residential properties are on pace to connect by the end of 2021.
- Work at the well sites will be starting in 2022. This includes upgrading the Lannon Estates well to municipal grade, rehabilitating the well at Whispering Ridge, and adding a third booster pump to Whispering Ridge.
- These projects make the entire system more reliable and add fire protection capacity.
- This winter, the Village will be exploring how to use USDA-RD contingency grant funds made possible due to the projects tracking under budget.
CONSTRUCTION UPDATE – 11/23/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN CONSTRUCTION UPDATE
- All water main and public water services have been installed and put into service. Please coordinate with Mid City to schedule completion of the private property work.
- Contact Isak Fruchtman to report any issues related to property damage as the result of the construction: 414.982.2300 x1535, Isak.Fruchtman@strand.com
- Pavement milling is scheduled to take place by the end of November. Paving may take place in November, weather permitting. Any paving not completed this fall will be rescheduled to springtime.
- Turf areas and landscaping disturbed by construction will be restored this year. Vinton will return in Spring to reseed any areas that have not germinated.
See the chart below for the anticipated schedule for other work areas.
CONSTRUCTION UPDATE – 11/19/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN CONSTRUCTION UPDATE
- Vinton currently anticipates completing all water main construction by the end of November.
- Contact Isak Fruchtman to report any issues related to property damage as the result of the construction: 414.982.2300 x1535, Isak.Fruchtman@strand.com
- Work is actively occurring on Good Hope Road, Diamond Drive, Hemlock Lane, Bay Street, State Street, Vine Street, Lake Street, Lannon Road, F and W Court, W Forest View Drive, N Parkview Drive, Edgewood Drive, and Circle Drive.
- All streets with trench patches will receive full width paving.
- Pavement milling is scheduled to take place by the end of November. Paving may take place in November, weather permitting. Any paving not completed this fall will be rescheduled to springtime.
- Turf areas and landscaping disturbed by construction will be restored this year. Vinton will return in Spring to reseed any areas that have not germinated.
See the chart below for the anticipated schedule for other work areas.
CONSTRUCTION UPDATE – 11/12/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN CONSTRUCTION UPDATE
- Vinton currently anticipates completing all water main construction by the end of November.
- Contact Isak Fruchtman to report any issues related to property damage as the result of the construction: 414.982.2300 x1535, Isak.Fruchtman@strand.com
- Work is actively occurring on Good Hope Road, Diamond Drive, Hemlock Lane, Bay Street, State Street, Vine Street, Lake Street, Lannon Road, F and W Court, W Forest View Drive, N Parkview Drive, Edgewood Drive, and Circle Drive.
- Pavement milling is scheduled to take place by the end of November. Paving may take place, weather permitting. Any paving not completed this fall will be rescheduled to springtime.
- Turf areas and landscaping disturbed by construction will be restored this year. Vinton will return in Spring to reseed any areas that have not germinated.
- The Well Upgrades project was awarded on 10/11. Construction will likely begin in November.
See the chart below for the anticipated schedule for other work areas.
CONSTRUCTION UPDATE – 11/05/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE
- Vinton currently anticipates completing all water main construction by the end of November, weather permitting.
- Vinton is using 5-6 construction crews in order to accomplish this.
- Mid-City has re-mobilized to Lannon to complete private property conversions to municipal water prior to 12/31/21.
- Work is actively occurring on Good Hope Road, Diamond Drive, Hemlock Lane, Bay Street, State Street, Vine Street, Lake Street, Lannon Road, F and W Court, W Forest View Drive, N Parkview Drive, Edgewood Drive, and Circle Drive.
- Pavement and landscape restoration will be occurring within the next couple of weeks.
- Turf areas disturbed by construction will be restored this year. Vinton will return in Spring to repair any areas that have not germinated.
- Expect temporary interruptions to driveway access. A project representative will knock on your door prior to driveway interruptions. If your driveway is blocked and you need access, step outside and ask a project representative. In most cases, access can be temporarily restored within 15 minutes.
- The Well Upgrades project was awarded on 10/11. Construction will likely begin in November.
See the chart below for the anticipated schedule for other work areas.
CONSTRUCTION UPDATE – 10/28/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE
- Vinton currently anticipates completing all water main construction by the end of November, weather permitting.
- Vinton is using 5-6 construction crews in order to accomplish this.
- Mid-City has re-mobilized to Lannon to complete private property conversions to municipal water prior to 12/31/21.
- Work is actively occurring on Good Hope Road, Diamond Drive, Hemlock Lane, Bay Street, State Street, Vine Street, Lake Street, Lannon Road, Edgewood Drive, and Circle Drive.
- Pavement restoration will be occurring within the next couple of weeks.
- Curb and gutter installation on Good Hope Road will occur next week. Residents effected by the interruption will receive notifications.
- Expect temporary interruptions to driveway access. A project representative will knock on your door prior to driveway interruptions. If your driveway is blocked and you need access, step outside and ask a project representative. In most cases, access can be temporarily restored within 15 minutes.
- The Well Upgrades project was awarded on 10/11. Construction will likely begin in November.
See the chart below for the anticipated schedule for other work areas.
CONSTRUCTION UPDATE – 10/15/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE
- Vinton currently anticipates completing all water main construction by the first week of December, weather permitting.
- Water main is currently being installed on Good Hope Road, Diamond Drive, Hemlock Lane, Bay Street, Edgewood Drive, and Circle Drive.
- Expect temporary interruptions to driveway access. A project representative will knock on your door prior to driveway interruptions. If your driveway is blocked and you need access, step outside and ask a project representative. In most cases, access can be temporarily restored within 15 minutes.
- Town Line Road will be closed through approximately 10/22 as pavement and landscape restoration is completed.
- Good Hope Road will have a traffic pattern shift through 11/22. During work hours, this may include a single lane with a flagger
- The Well Upgrades project was awarded on 10/11. Construction will likely begin in November.
See the chart below for the anticipated schedule for other work areas.
CONSTRUCTION UPDATE – 10/05/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE
- Town Line Road will be closed through approximately 10/22.
- Good Hope Road will have a traffic pattern shift from 10/4 through 11/22.
- Edgewood & Circle Dr. will begin on 10/11 and continue through 11/19.
- Diamond Drive, near Good Hope Rd., will begin approximately on 10/18.
The construction notification for this project can be found here.
See the chart below for the anticipated schedule for other work areas.
CONSTRUCTION UPDATE – 9/09/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE
- Main Street will be closed to Westbound traffic through approximately September 20, 2021.
- Town Line Road will be closed to Northbound traffic through approximately September 20, 2021 and then closed to all thru traffic through approximately October 22, 2021.
- Restoration in Work Zone C, W. Main Street from Townline Road to Flagstone Pass will be completed by 9/11.
- Work through the Lannon Elementary School Easement was completed.
- Water main on Lannon Rd. (Work Zone I) from Lannon Elementary to Forestview was completed. However, the remaining water main to Diamond Drive and public water service laterals are not planned to be installed until October. Restoration of the trenched area will take place the week of 9/13.
- Restoration in Work Zone G, through the roundabout, is in progress and will be completed .
- See the chart below for the anticipated schedule for other work areas.
The construction notification for this project can be found here.
See the chart below for the anticipated schedule for other work areas.
CONSTRUCTION UPDATE – 9/02/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE
- Main Street will be closed to Westbound Traffic through approximately October 1st or later.
- Work Zone C, W. Main Street from Townline Road to Flagstone Pass:
- Water main has been installed
- Restoration will take place the week of 9/7.
- Work through the Lannon Elementary School Easement began and will be completed by September 3.
- Work on Lannon Rd. (Work Zone I) began. However, public water service laterals are not planned to be installed until October. Restoration of the trenched area will take place the week of 9/7.
- Work Zone G, through the roundabout, will begin the week of 9/7.
- See the chart below for the anticipated schedule for other work areas.
CONSTRUCTION UPDATE – 8/27/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE
- Work Zone C, W. Main Street from Townline Road to Flagstone Pass:
- Westbound lane closure and partial detour is in effect.
- No westbound traffic is allowed.
- Water main installation will continue through early September.
- Work through the Lannon Elementary School Easement began and will be completed by September 3.
- See the chart below for the anticipated schedule for other work areas.
SEVERE WEATHER UPDATE – 8/12/21
- The Village’s municipal water system has backup power supplied by a permanent, natural gas generator.
- During the recent storms, the wellhouse’s main power supply was interrupted.
- The power supply automatically switched over to the natural gas generator.
- The well and booster pumps continue to run on the generator without issue.
- Water utility customers have reported no disruption to water service during this event.
CONSTRUCTION UPDATE – 8/19/21
Questions?
Onsite Construction Representative: Isak Fruchtman (Strand), 414.982.2300 x1535
Overall Project Manager: Ben Wood, P.E., (Strand), 414.271.0771
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE
- Work Zone C, W. Main Street from Townline Road to Flagstone Pass:
- Westbound lane closure and partial detour is in effect.
- No westbound traffic is allowed.
- Water main installation started the week of 8/2 and will continue for the rest of August.
- See the chart below for the anticipated schedule for other work areas.
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE – 8/06/21
- Work Zone A, Good Hope Road from Main Street to Lannon Road:
- Work is complete with minor restoration to continue.
- Work Zone K, Good Hope Private Driveway (West of Lannon Elementary):
- Work is complete with minor restoration to continue.
- Work Zone C, W. Main Street from Townline Road to Flagstone Pass:
- Westbound lane closure and partial detour started 8/2.
- Water main installation started the week of 8/2.
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE – 7/8/21
- Lake Street storm sewer lining is being conducted by Visu-Sewer as part of the overall project and will take place during the month of July
- Work Zone A, Good Hope Road from Main Street to Lannon Road, will continue.
- Water main and public lateral installation are anticipated be completed by 7/9, with disinfection and testing completed by 7/14.
- Contractor will begin grading and installing curb and gutter the week of 7/12.
- Work Zone K, Good Hope Private Driveway (West of Lannon Elementary), will begin the week of 7/12.
- See the chart below for the anticipated schedule for other work areas. Note: On-going schedule modifications are taking place in order to accommodate Cars on Main and Lannon 90th festivities.
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE – 7/2/21
- No work will take place from Saturday, 7/3 through Monday, 7-5.
- Lake Street storm sewer lining is being conducted by Visu-Sewer as part of the overall project and will take place during the month of July
- Work Zone A, Good Hope Road from Main Street to Lannon Road, will continue.
- Water main and public lateral installation are anticipated be completed the week of 7/6, with disinfection and testing completed by 7/14.
- Contractor will begin grading and installing curb and gutter by approximately 7/8.
- Work Zone K, Good Hope Private Driveway (West of Lannon Elementary), will begin on 7/8.
- See the chart below for the anticipated schedule for other work areas.
PUBLIC WATER MAIN AND WELL CONSTRUCTION UPDATE – 6/7/21
- USDA-RD has delivered “closing instructions” to the Village, signifying their approval of the application documents.
- The Village Board awarded the public water main construction bid to Vinton Construction Company of Two Rivers, WI.
- Vinton’s low bid of $5,459,392.50 was less than the USDA-RD budget.
- Water Main Construction should start by the end of June or early July.
- The area that Vinton plans to start work will be updated on this page as soon as the information is available.
- Water main installation is scheduled for completion by the end of 2021.
- Roadway construction is scheduled for completion by June of 2022.
- Well upgrades are expected to proceed in the Fall of 2021.
WELL ABANDONMENT GRANT UPDATE – 12/15/20
- Well estimate forms are at Village Hall and on the Village’s website.
- Well Abandonment Grant applications are due approximately 1 month prior to the start of well abandonment work on your property.
- Applications are not due by December 10th as indicated in the letter sent to residents impacted by the project.
- DNR indicated they need to be submitted before the work is done.
- Mid-City and CTW do not plan to start well abandonments until March.
- Please apply by the end of February 2021.
- If your taxable income will be less in 2020 than it was in 2019, it is to your advantage to wait until January to submit your well abandonment grant form. Well Abandonment Grant eligibility is based on the income of the most recent full year’s taxable income. Contact Sandy Chancellor at DNR for special circumstances such as a recent change in employment: (608) 275-3206.